Welcome to EPCOR Our site is customized by location. Please select the region of your service and we’ll remember your selection for next time.
Select location

Our site is customized by location. Please select the region of your service and we’ll remember your selection for next time.

Change a country
Country Flag Canada
Country Flag United States

Select a region for customized content and rates

Mouse hover over any region to see the map here
Edmonton
All Alberta locations except Edmonton
French Creek
Aylmer and area
Collingwood and area
Kincardine and area
Select a state

Looks like you're in Canada

Looks like you're in the United States

Change country
Country Flag Canada
Country Flag United States

Select a region for customized content and rates

Mouse hover over any region to see the map here
Edmonton
All Alberta locations except Edmonton
French Creek
Aylmer and area
Collingwood and area
Kincardine and area

Select a region for customized content and rates

Select a region for customized content and rates

Choose your location
To view this page, set your location to:
Country Flag Country Flag
This page doesn’t match your location
To view this page, you must change your location to:
Country Flag Country Flag
Choose your location
To view this page, you must set your location to:
Country Flag Country Flag

Duggan Tunnel Replacement

ON THIS PAGE

Having safe, reliable utility services is a critical part of day-today life in the community.

The existing Duggan sanitary tunnel provides service to neighbourhoods in southwest Edmonton and has been identified for replacement. This will see construction of a new sanitary tunnel to service neighbourhoods from Steinhauer up to Bonnie Doon.

The alignment of the new tunnel is along 111 Street from Saddleback Road/29A Avenue, east along 34 Avenue, and then north on 106 Street to north of L.Y. Cairns School.

EPCOR is aware of consistent sewer odour issues in several neighbourhoods along the alignment of the Duggan Tunnel, particularly in Steinhauer. This project is part of EPCOR’s Corrosion and Odour Reduction Strategy (CORe). The strategy aims to understand and mitigate sewer odour issues and will result in significantly reduced sewer odour city-wide by 2031. With completion of the new tunnel, we expect the major cause of how odour is formed and pushed out into the communities to be notably diminished.

The majority of the work will be underground using a tunnel boring machine (TBM). However, there will be multiple worksites (shaft locations) along the tunnel alignment to allow the TBM to be lowered underground to excavate, turn corners, and be removed when tunneling is complete.

Project overview

Project background

The Duggan sanitary sewer line services neighbourhoods in southwest Edmonton, from Steinhauer up to Bonnie Doon. Construction on the new Duggan Tunnel began in March 2023 and is expected to be completed by Summer 2025.

About the Duggan Tunnel

The Duggan tunnel sanitary sewer moves wastewater from south Edmonton to the Gold Bar Wastewater Treatment Plant. The existing sewer is approximately 30 metres deep and was originally built by hand.

The new tunnel has been identified for replacement due to poor condition and to help address odour in the area. The existing Duggan sanitary tunnel services the Edmonton region highlighted on the map:

Odour reduction

​How are we helping with odour in your neighbourhood

EPCOR is aware of consistent sewer odour issues in several neighbourhoods along the alignment of the Duggan Tunnel, particularly in Steinhauer. This project is part of EPCOR’s Corrosion and Odour Reduction Strategy (CORe). The strategy aims to understand and mitigate sewer odour issues and will result in significantly reduced sewer odour city-wide by 2031. With completion of the new tunnel, we expect the major cause of how odour is formed and pushed out into the communities to be notably diminished.

Why is there odour and how will the project help?

The existing Duggan tunnel serves as both a sanitary and storage tunnel and is just over three kilometers long. This means that sanitary flows are stored in the tunnel during wet weather events.

The existing Duggan tunnel has various shifts in depth along the alignment. When built in the 1960s, crews didn’t have the equipment or technology to easily tunnel through the existing sand layer, so they had to tunnel above it or below it. This variation in depth increases the movement of the sanitary flow (up and down), which increases the amount of odour generated. The new tunnel will flow by gravity (not up and down), which will reduce the amount of odour pushed out into the communities.

How odour develops in the existing Duggan tunnel:​

Other ways we are helping with odour

What else are we doing?

Sometimes, creating a change in one area can increase sewer odours in another. This is why EPCOR has a city-wide strategy and why the work must occur in a specific sequence.

Some steps have already begun, allowing for better access to infrastructure to inspect lines and investigate odour issues:

  • Two access manholes were built along 104A Street near 48 Avenue to support inspection, monitoring and cleaning of the sanitary system. This work was completed in May 2020
  • Projects have been completed/underway to reduce odour issues at three local pump stations (Kaskitayo, Blackburn and Twin Brooks). These projects focus on moving the flow of wastewater more quickly to reduce stagnation
  • Four access manholes in Empire Park and Pleasantview were completed, allowing for better access and cleaning
  • Manhole seals and airflow control devices have been installed at the intersection of 34 Avenue and 106 Street, and at several key junctions along 106 Street from 34 Avenue to Whitemud Drive
  • In 2021, a surface air quality monitor was installed at the 34 Avenue and 106 Street intersection to monitor the concentration of odours in the area​

Residents are encouraged to report an issue any time an odour is overly strong by calling EPCOR Trouble at 780-412-4500. This helps us to track the odour to look for patterns and potential solutions.

Project schedule

Construction began in March 2023 with completion anticipated by Summer 2025.

Causes of possible schedule delays

While we always do our best to plan construction and abide by construction timelines communicated to the public, unexpected events can potentially occur which may delay the schedule. Some of these factors are:

Ground conditions and boulders

Geotechnical investigations have been completed along the alignment and we anticipate that the ground conditions are favourable for tunneling. However, there is a risk the tunnel boring machine (TBM) could encounter harder soil, boulders or soupy sand, which could slow down progress.

Extreme weather

Extreme weather, including severe cold, heavy rains, high winds and lightning make working unsafe. During these conditions, the site will be shut down.

Relocation of existing utilities

The start date of the project is dependent on relocation of the utilities, including a water main relocation at Worksite #5. There may be some disruption to local services; however, more information will be provided before the work starts.

Project map

Impacts to you

This project is broken down geographically into five zones which follow the alignment of the new tunnel:

Zone A – 111 Street from Saddleback Road/29A Avenue to 34 Avenue

Zone A background

Three worksite locations will support the construction process, with timelines as follows:

  • Worksite #1A - Northbound on 111 Street at 29A Avenue – Spring 2023 to Summer 2025
  • Worksite #1B - 111 Street southbound, left turn lane onto 29A Avenue – Fall 2023 to Summer 2025
  • Worksite #2 - In the green space east of 111 Street and south of 34 Avenue – April 2023 to Summer 2025

Please note, impacts may change based on City of Edmonton Traffic approvals. Advanced notification will be provided to residents and businesses in the local area before work begins.

Traffic

Worksite 1A​

  • ​​One northbound lane on 111 Street, north of Saddleback Road/29A Avenue will be closed
  • The right hand turning lane from westbound 29A Avenue onto northbound 111 Street will be closed
  • Vehicles will be able to turn right, onto the left northbound lane from the intersection

Worksite 1B

  • No parking will be permitted on the south side of 45 Avenue east of 106 Street
Sidewalks/walkways

​Worksite 1A

  • ​The sidewalk on the east side of 111 Street north of 29A Avenue will be closed
  • Pedestrians will be detoured to the west side of 111 Street
Other

Worksite 1A

  • ​​Bus stop #4582 will be relocated on the east side of 111 Street to north of the work area

Worksite 2

  • ​A portion of the green space on the southeast corner of 111 Street and 34 Avenue will be utilized as a work area. The area will be fully fenced and secured
Working hours

Typical hours of work will be from 7:00 a.m. to 7:00 p.m., Monday to Saturday. If required, these hours may be extended, and construction may occur on Sundays from 9:00 a.m. to 5:00 p.m.

During tunneling, the tunnel boring machine will be running 24/7 at Worksite #2.

Haul route

Trucks and equipment will access all the worksites from 111 Street. Temporary lanes closures may be in effect.

​Zone B – 34 Avenue from 111 Street to 106 Street

Zone B background

Two worksite locations will support the construction process, with timelines as follows:

  • ​Worksite #3 - Eastbound on 34 Avenue, between 111 Street and 106 Street – Completed
  • Worksite #4 - Northbound ​on 106 Street and north of 34 Avenue – April​ 2023 to Summer 2025

Please note, impacts may change based on City of Edmonton Traffic approvals. Advanced notification will be provided to residents and businesses in the local area before work begins.

Traffic

Worksite 3

  • ​Two eastbound lanes on 34 Avenue between 111 Street and 108 Street will be closed. The westbound lanes will be converted to one lane in each direction to allow two-way traffic

Worksite 4

  • ​One northbound lane on 106 Street from the intersection at 34 Avenue and heading north past the work area will be closed
  • T​he westbound curb lane on 34 Avenue at 106 Street will be closed
Sidewalks/walkways

​Worksite 4

  • ​The shared-use path at the northeast corner of the intersection at 34 Avenue and 106 Street will be closed. Pedestrians will be detoured south of the worksite
  • No crossing will be permitted across 106 Street on the north side of 34 Avenue. Pedestrians will be detoured to the south side of the intersection to cross
Other

​Worksite 3

  • A portion of the greenspace along the south side of 34 Avenue between 111 Street and 108 Street will be utilized as a work area. The area will be fully fenced and secured
Working hours

Typical hours of work will be from 7:00 a.m. to 7:00 p.m., Monday to Saturday. If required, these hours may be extended, and construction may occur on Sundays from 9:00 a.m. to 5:00 p.m. During tunneling, the tunnel boring machine will be running 24/7 at Worksite #3.

Haul route

Trucks and equipment will access all the worksites from 34 Avenue. Temporary lane closures may be in effect.

​Zone C – 106 Street from 36A Avenue to 38 Avenue

Zone C background

Two worksite locations will support the construction process, with timelines as follows:

  • ​Worksite #5 - Intersection of 106 Street and 36A Avenue – Summer 2023 to Summer 2025
  • Worksite #6 - Northbound on 106 Street and north of 36A Avenue – Summer 2023 to Summer 2025

Please note, impacts may change based on City of Edmonton Traffic approvals. Advanced notification will be provided to residents and businesses in the local area before work begins.

Traffic

Worksite 5​

  • ​​A full road closure of 36A Avenue at 106 Street

Worksites 5 & 6

  • Two northbound lanes on 106 Street between 36A Avenue and 38 Avenue will be closed. The southbound lanes will be converted to one lane in each direction to allow two-way traffic
  • Access will be ma​intained to Garden Grove Condominiums from 106 Street
Sidewalks/walkways

Worksite 5

  • ​No crossing will be permitted across 106 Street on the north side of 36A Avenue. Pedestrians will be detoured to the south crossing
  • No crossing will be permitted across 36A Avenue on the east side of 106 Street. Pedestrians will be detoured to the west side of 36A Avenue
Other

​Worksites 5 & 6

  • ​​No parking will be permitted on the west side of 106 Street north of 36A Avenue for approximately 75 metres alongside Duggan Elementary School
Working hours

Typical hours of work will be from 7:00 a.m. to 7:00 p.m., Monday to Saturday. If required, these hours may be extended, and construction may occur on Sundays from 9:00 a.m. to 5:00 p.m. During tunneling, the tunnel boring machine will be running 24/7 at Worksite #5.

Haul route

​Trucks and equipment will access all the worksites from 106 Street. Temporary lane closures may be in effect. No hauling will occur during school drop off and pick up times.

​Zone D – 106 Street from 40 Avenue to Whitemud Drive

Zone D background

Four worksite locations will support the construction process, with timelines as follows:

  • ​​​Worksite #7 - Intersection of 106 Street and 40 Avenue – Completed
  • Worksite #8 - Southbound on 106 Street and south of 41 Avenue – Summer 2023 to Spring 2025
  • Worksite #9 – Southbound on 106 Street and south of Whitemud Drive – Fall 2023 to Spring 2025
  • Worksite #10 – Northbound on 106 Street and south of Whitemud Drive – Early 2024 to Spring 202​5

Worksites 7 & 8

Worksites 9 & 10

Please note, impacts may change based on City of Edmonton Traffic approvals. Advanced notification will be provided to residents and businesses in the local area before work begins.

Traffic

Worksites 7 & 8

  • ​The southbound left hand turning lane from 106 Street onto 40 Avenue will be closed. Vehicles will be able to turn left from the one remaining open lane
  • One northbound and one southbound lane will be closed on 106 Street from 40 Avenue to north of DS MacKenzie Junior High. One lane will remain open in each direction
  • No left hand turns will be permitted from the Duggan Mall exits onto southbound 106 Street

Worksites 9

  • ​One southbound lane on 106 Street between 42 Avenue and Whitemud Drive will be closed

​Worksite 10

  • ​The northernmost access into Whitemud Crossing from 106 Street south of Whitemud Drive will be closed
  • The northbound right turn lane onto eastbound Whitemud Drive will be closed. Vehicles will be able to turn at the intersection
Sidewalks/walkways

Worksite 7

  • ​The crosswalk across 106 Street on the north side of 40 Avenue will be closed. Pedestrians will be det​​our to the north

Worksite 9

  • The sidewalk on the west side of 106 Street between 42 Avenue and Whitemud Drive will be closed. Pedestrians will be detoured to the east side
Other

​Worksites 7 & 8

  • ​​DS MacKenzie Junior High drop off and pick up area on the west side of 106 Street will be reduced
  • A reduced area will remain open between Worksite #7 and Worksite #8 for student drop off and pick up
Working hours

Worksites 7 & 8 

Typical hours of work will be from 7:00 a.m. to 7:00 p.m., Monday to Saturday. If required, these hours may be extended, and construction may occur on Sundays from 9:00 a.m. to 5:00 p.m. During tunneling, the tunnel boring machine will be running 24/7 at Worksite #7 and #8.​

Worksites 9 & 10

Typical hours of work will be from 7:00 a.m. to 7:00 p.m., Monday to Saturday. If required, these hours may be extended, and construction may occur on Sundays from 9:00 a.m. to 5:00 p.m.​

Haul route

Worksites 7 & 8

Trucks and equipment will access the worksites from 106 Street and 40 Avenue. Additional temporary lane closures may be in effect. Hauling activity will not be performed during student pick-up and drop off times as identified by DS MacKenzie Junior High and St. Augustine.

Worksites 9 & 10

Trucks and equipment will access all the worksites from 106 Street. Temporary lane closures may be in effect.

​Zone E – 106 Street and 45 Avenue to L.Y. Cairns​

Zone E background

Three worksite locations will support the construction process, with timelines as follows:

  • ​Worksite #11 - Intersection of 45 Avenue and 106 Street – Completed
  • Worksite #12 - 45 Avenue east of 106 Street – Fall 2023 to Spring 2025
  • Worksite #13 – 104A Street north of 45 Avenue – Early 2025 to Summer 2025​

Please note, impacts may change based on City of Edmonton Traffic approvals. Advanced notification will be provided to residents and businesses in the local area before work begins.

Traffic

Worksite 11​

  • One northbound lane and one southbound lane on 106 Street between Whitemud Drive and 45 Avenue will be closed
  • No left hand turns will be permitted at the following:
    • ​From southbound 106 Street onto eastbound 45 Avenue
    • From westbound 45 Avenue onto southbound 106 Street

Worksite 12​​

  • No parking will be permitted on the south side of 45 Avenue east of 106 Street

Worksite 13

  • The southbound lane on 104A Street between 47 Avenue and 48 Avenue will be closed. Vehicles will be directed to yield to oncoming traffic to maintain two-way traffic
Other

​Worksite 12

  • L.Y. Cairns School drop off and pick up area on 45 Avenue will be reduced to one lane
  • ​Visitor parking at L.Y. Cairns School on 45​​ Avenue will be partially reduced
  • Increased odour may be present while construction is underway
  • No hauling activity will occur during school drop off and pick-up times at L.Y. Cairns
Working hours

Typical hours of work will be from 7:00 a.m. to 7:00 p.m., Monday to Saturday. If required, these hours may be extended, and construction may occur on Sundays from 9:00 a.m. to 5:00 p.m. During tunneling, the tunnel boring machine will be running 24/7 at Worksite #11.​

Haul route

​Trucks and equipment will access all the worksites from 106 Street and 104A Street. Temporary lanes closures may be in effect during these times.​

​What to expect during construction

Noise c​ontrol
  • Work will create typical noise associated with construction
  • Noise mitigation measures, such as noise control panels around the equipment, will be implemented to comply with City standards
  • Heavy trucks will be moving through residential streets
Safety
  • ​Safety is our first priority for our site workers and community members. All work areas will be fenced off and secured, and flagging personnel will be used where necessary
Weather
  • ​Work may be delayed due to extreme weather, such as lightning, cold temperatures, and wind. Updates will be provided if original timelines are adjusted
Hours of work
  • During shaft construction, typical hours of work will be 7:00 a.m. to 7:00 p.m. Monday – Saturday. If required, these hours may be adjusted or extended, and construction may occur on Sundays from 9:00 a.m. to 5:00 p.m.
  • During the tunneling period, there will be continuous work 24-hours-a-day, 7-days-a-week
  • 24/7 tunneling will only occur at Worksites #2, #3, #5, #7, #8 and #11. Advance notification will be provided to residences and businesses near the work area prior to the start of 24/7 tunneling
Odour
  • There may be odour during the work around L.Y. Cairns School
Parking
  • Vehicles related to the construction may be parked on the road near the construction sites
Visual impacts
  • You can expect to see activity that is typical to construction, including company/contractor vehicles and equipment
  • A combination of excavators, loaders, skid steers, cranes, and tandem trucks, as well as other equipment at worksite locations
  • There will also be a two-story soil separator at Worksites #2, #3, #5, #7, #8 and #11 used to manage soil from tunneling operations

Equipment on site

Tunnel Boring Machine

We'll be using a Tunnel Boring Machine (TBM) at during this project. The tunneling process occurs underground using a TBM; however, shafts are required at the start and end points.

During tunneling, it may appear not much work is occurring; however, this is being done underground.

​What is​ a TBM?

A machine used to excavate tunnels by breaking the surrounding soil/earth/rock to create a large diameter tunnel. Pipe is then laid behind the tunnel as it is excavated underground.

Example of a micro-tunnel boring machine (TBM) used during construction.

How big is the ​​TBM?

The TBM being used for this project is 4.5 metres in length, weighs approximately 30 tonnes and is 2.7 metres in diameter.

How fast does a TBM tunnel?

It is anticipated that the TBM will progress, on average, at a speed of about ten metres per day in the expected conditions. Please note, timelines are estimates and may change on construction and soil conditions.

W​​hy does the TBM need to operate 24 hours a day?

The TBM operates under a pressure system to move forward. This is facilitated by the use of a slurry (water and material mixture) to lubricate the pipes and reduce friction. When tunneling stops, the slurry may harden and cause the TBM to be unable to be pushed forward. As a result, 24/7 operations are required during the tunnel period of construction. 24/7 work will occur at worksites #2, #3, #5, #7, #8 and #11.

​What is a slur​ry separation machine?

A slurry separation machine is a large piece of equipment (approximately two stories tall) used to mange soil removal. The machine separates the solids from slurry, so that the water can be recycled back to the TBM. The machine operates 24-hours-a-day while the TBM is tunneling. Noise mitigation panels will be used to dampen the noise generated by the machine. This machine will be on site at worksites #2, #3, #5, #7, #8 and #11.

Example of a slurry separation machine used onsite during tunneling activities.

Questions?

​Your questions are important to us.

Contact EPCOR

Phone: 780-412-4200
Email: epcorprojects@epcor.com

This site uses cookies to provide a better user experience and for advertising purposes. By using our website, you accept our use of cookies. Visit our Privacy Policy for more details.